The Company
Milestones
Date
Events
Oct', 2009 End of pioneer status which granted Nigeria LNG exemption from Companies Income Tax and Education Tax during the first ten years of production
Sept', 2009 NLNG celebrates twenty years since incorporation and ten years of production
May, 2008 Nigerianisation of Managing Director position
Dec', 2007 Start-Up T6
Oct', 2007 First Butane cargo loaded for domestic market.
Jun', 2007 T6 fully operational.
Dec', 2006 1000th Cargo.
Feb', 2006 Start-Up of Train 5.
Nov', 2005 Start-Up of Train 4.
Jul', 2004 Final Investment Decision (FID) by shareholders for Train 6 (NLNGSix).
Feb' 9, 2004 Inauguration of The Nigeria Prize for Literature, The Nigeria Prize for Science, (worth $20,000 each), and The NLNG Charity Ball.
Jun' 25, 2003 First Shipment of LPG from NLNG Plant, Bonny
Feb', 2003 Start-up of the LPG Facility
Dec' 21, 2003 Signing of the $1.6 billion loan for NLNGPlus
Dec' 17, 2002 First LNG Shipment from Train 3, three months ahead of schedule
Nov' 28, 2002 Commencement of LNG production from 3rd Train
Nov' 7, 2002 Train 3 Plant Ready for Start Up
Mar' 22, 2002 EPC Contract Award to TSKJ for Trains 4 & 5
Mar' 20, 2002 Final Investment decision (FID) for Trains 4 and 5
Oct' 1, 2001 Commencement of Contract Year
Sept' 30, 2001 End of Build Up Period
Sept' 18, 2001 Signed Memorandum of Understanding for Micro Credit Scheme
Feb' 4, 2001 Export of 100th Cargo
Sept' 21, 2000 Plant Commissioning Ceremony
Aug' 5, 2000 Export of 50th Cargo
May 25, 2000 Export of first spot cargo
Apr' 4, 2000 Export of First Condensate Cargo
Mar' 29, 2000 Loading of Initial Supply Period (ISP)
Oct' 9, 1999 Export of First Cargo
Sept' 15, 1999 Commencement of Production
Aug' 1999 Train Two Plant Ready for Start-up
Feb' 1999 Final Investment Decision by Shareholders for Third Train

Sept' 1998

Completion of Gas Transmission System (GTS)
Jan' 1996 Commencement of Plant Construction
Nov' 1995 Final Investment Decision (FID) by Shareholders for base project
May 17, 1989 Incorporation of Nigeria LNG Limited

Newsarea
Feb, '10  The call has now been made for entries for the Nigeria Prize for Science and the Nigeria Prize for Literature, for more details...
...........................................
 
Mar 31, '10  March 31 is the deadline for submission of entries for the Nigeria Prize for Science and the Nigeria Prize for Literature. For more information ... 
 
Special reports
"The society which scorns excellence in plumbing as a humble activity and tolerates shoddiness in philosophy because it is an exalted activity will have neither good plumbing nor good philosophy: neither its pipes nor its theories will hold water.' We agree with this quote from John Gardner, so what are we doing about it? Find out in the latest edition of our CSR digest..."
Scam Alerts
It has come to our attention that some individuals are contacting people via e-mail and or publications in the internet claiming to be recruitment agents of  NLNG...  

All content on this website is copyright Nigeria LNG Limited. All rights reserved.