HISTORY

Nigeria LNG was incorporated in 1989. In November 1995, a Final Investment Decision (FID) was signed by the Shareholders to build a Liquefied Natural Gas Plant in Finima, Bonny Island in Rivers State.

In December 1995, a consortium of engineering firms comprising Technip, Snamprogetti, M.V. Kellog and Japan Gas Corporation (TSKJ) was awarded a turnkey Engineering, Procurement and Construction (EPC) contract for the construction of the Plant, the Gas Transmission System and the Residential Area.

Construction of the plant site commenced in February 1996 and by August 1999, one of the two trains (Train 2) was completed.
On August 12 of the same year, the plant was ready for start-up, and production of LNG commenced on September 15. The second train of the Base Project, Train 1, came on stream on February 27, 2000. Train 3 came into operations in November 2002.

NLNGPlus, comprising Trains 4 and 5, came on stream in November 2005 (for Train 4) and February 2006 (for Train 5).

NLNG Six, came on stream in December 2007.

The plant has rapidly and successfully made the transition from a construction project to a stable production operation, with a robust delivery chain underpinned by relentless focus on asset integrity and HSE assurance.
This has made NLNG to achieve, within a short span, the status of a very reliable supplier of LNG in the Atlantic Basin, serving the European and North American markets.


TIMELINE

Date               Events
Oct'      2009 End of pioneer status which granted Nigeria LNG exemption from Companies Income Tax and Education Tax during the first ten years of production
Sep'     2009 NLNG celebrates twenty years since incorporation and ten years of production
May      2008 Nigerianisation of Managing Director position
Dec'     2007 Start-Up T6
Oct'      2007 First Butane cargo loaded for domestic market.
Jun'      2007 T6 fully operational.
Dec'     2006  1000th Cargo.
Feb'     2006 Start-Up of Train 5.
Nov'     2005 Start-Up of Train 4
Jul'       2004 Final Investment Decision (FID) by shareholders for Train 6 (NLNGSix).
Feb'  9 2004 Inauguration of The Nigeria Prize for Literature, The Nigeria Prize for Science, (worth $20,000 each), and The NLNG Charity Ball.
Jun' 25 2003 First Shipment of LPG from NLNG Plant, Bonny
Feb'      2003 Start-up of the LPG Facility
Dec' 21 2003 Signing of the $1.6 billion loan for NLNGPlus
Dec' 17 2002 First LNG Shipment from Train 3, three months ahead of schedule
Nov' 28 2002 Commencement of LNG production from 3rd Train
Nov'  7   2002 Train 3 Plant Ready for Start Up
Mar' 22  2002 EPC Contract Award to TSKJ for Trains 4 & 5
Mar' 20  2002 Final Investment decision (FID) for Trains 4 and 5
Oct'  1    2001 Commencement of Contract Year
Sep' 30  2001 End of Build Up Period
Sep' 18  2001 Signed Memorandum of Understanding for Micro Credit Scheme
Feb'  4    2001 Export of 100th Cargo
Sep' 21  2000 Plant Commissioning Ceremony
Aug'  5    2000 Export of 50th Cargo
May 25   2000 Export of first spot cargo
Apr' 4      2000 Export of First Condensate Cargo
Mar' 29   2000 Loading of Initial Supply Period (ISP)
Oct' 9     1999 Export of First Cargo
Sep' 15  1999 Commencement of Production
Aug'        1999 Train Two Plant Ready for Start-up
Feb'        1999 Final Investment Decision by Shareholders for Third Train
Sep'        1998 Completion of Gas Transmission System (GTS)
Jan'         1996 Commencement of Plant Construction
Nov'         1995 Final Investment Decision (FID) by Shareholders for base project
May 17    1989 Incorporation of Nigeria LNG Limited
 



 
 

 